  • Rail temperature
  • Rail vibration
  • Points load pin
  • Clamp lock power pack monitoring
  • Points position monitoring

 

Notewarning

 Special care must be taken when attaching sensors to rails, pointwork, point machines or anything electrically connected to them.

...

Sensor requirements:

  • Each sensor must have electrical isolation between the 4-20mA output and the trackwork to a minimum of 4M Ohms at 250V.
  • 250mA fuses must be provided in each leg of the current loop.
  • Only Network Rail approved points load pins may be used.
  • When monitoring the pressure in clamp lock power packs, only pressure sensors approved by the manufacturer of the power pack must be used.
  • Where sensors are attached to both rails, a risk assessment must be carried out to ensure that there is no risk of a track circuit being false fed

...