The flow chart below summarises the steps required to successfully install and commission the S-LX system.

Detailed descriptions of each step can be found below

It is recommended that installation diagrams are prepared prior to installation and referred to throughout the installation process.

The S-LX system is highly flexible and can be applied to many serial port and Ethernet remote monitoring applications and is not limited to those listed below.

Please contact MPEC to discuss any potential further applications

If trouble is encountered please contact MPEC technical support for further assistance:

  • Telephone: 01332 363 979. Available Monday to Friday 8 AM to 4 PM UK time.

  • Email: support@mpec.co.uk. Response typically within 24 hours.

System Overview

Pre

Prepare Overlay Diagrams

Unbox & Mount the S-LX system

Antenna Installation

Connect AC Power Supply

Connect Serial or Ethernet Connection

Commissioning

Energise Power Supply

Check for Data Transmission

Check for Cellular Modem Transmission