Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 2 Next »

The flow chart below summarises the steps required to successfully install and commission the S-LX system.

Detailed descriptions of each step can be found below

It is recommended that installation diagrams are prepared prior to installation and referred to throughout the installation process.

If trouble is encountered please contact MPEC technical support for further assistance:

  • Telephone: 01332 363 979. Available Monday to Friday 8 AM to 4 PM UK time.

  • Email: support@mpec.co.uk. Response typically within 24 hours.

System Overview

Prepare Overlay Diagrams

Unbox & Mount the S-LX system

Antenna Installation

Connect AC Power Supply

Connect Serial or Ethernet Connection

Commissioning

Energise Power Supply

Check for Data Transmission

Check for Cellular Modem Transmission

  • No labels