  • Commissioning of the device can be split into three stages.

  • If issues are discovered, refer to the Trouble Shooting & Maintenance section.

  • S-LX Indication summary

...

Energise Power Supply

  • Energise the main power supply and check:

    • HZS device Power Indication illuminates

    • S-LX device Power Indication illuminates

    • S-LX device then begins boot sequence. This can take up to one minute

    • S-LX Run Indication begins to flash. The should continue to flash whilst the device is operating

    • The S-LX Error Indication will illuminate during boot.

    • The S-LX Error indication will then extinguish once the boot sequence is complete

...