The flow chart below summarises the steps required to successfully install and commission the S-LX system.

Detailed descriptions of each step can be found below

It is recommended that installation diagrams are prepared prior to installation and referred to throughout the installation process.

If trouble is encountered please contact MPEC technical support for further assistance:

  • Telephone: 01332 363 979. Available Monday to Friday 8 AM to 4 PM UK time.

  • Email: support@mpec.co.uk. Response typically within 24 hours.

Drawio
zoom1
simple0
inComment0
pageId2401730561
custContentId2404614150
lbox1
diagramDisplayNameUntitled Diagram.drawio
contentVer1
revision1
baseUrlhttps://mpec.atlassian.net/wiki
diagramNameUntitled Diagram.drawio
pCenter0
width801
links
tbstyle
height1256

System Overview

Prepare Overlay Diagrams

Unbox & Mount the S-LX system

Antenna Installation

Connect AC Power Supply

Connect Serial or Ethernet Connection

Commissioning

Energise Power Supply

Check for Data Transmission

Check for Cellular Modem Transmission